Rough-In Plumbing for Nashville Additions, ADUs & New Layouts

New bathrooms, basement finishes, ADUs, and kitchen islands — rough-in plumbing that passes inspection first time. — serving Nashville and surrounding Davidson County communities.

Rough-In Plumbing for Additions & New Layouts in Nashville

Nashville's ADU ordinance — one of the most permissive in the Southeast since Metro Council's 2022 expansion — has created a significant new category of investor plumbing work. Adding a secondary unit to a Davidson County property requires a full rough-in of kitchen and bath plumbing, Metro Water Services meter application (the long-lead item), and coordination with the main house water service to avoid cross-connection issues. We handle the full permit and coordination stack for Nashville ADU plumbing so investors can focus on the renovation — not the bureaucracy.

Why Nashville Properties Need This Service

  • Metro Water Services new meter lead times of 4–8 weeks for ADU secondary connections
  • Existing main house sewer capacity that may be undersized for added ADU fixture load
  • Basement rough-ins requiring ejector pump systems when below the main sewer elevation
  • Historic district coordination for additions to East Nashville, Germantown, or Sylvan Park properties
  • Permit sequencing complexity — plumbing permit depends on building permit which depends on zoning approval

What's Included

  • Full DWV and supply rough-in for new bathrooms, kitchens, and additions
  • ADU (accessory dwelling unit) plumbing for Nashville's growing secondary unit market
  • Basement bathroom rough-ins using ejector pump systems where needed
  • Coordinated scheduling with framing crews for zero-delay integration
  • Stamped drawings and permit support for Davidson County building department
  • Wet bar, laundry, and outdoor kitchen rough-ins for investor upgrades
Nashville Investor Tip

For Nashville ADU projects, start the Metro Water meter application the day your building permit is submitted — not after it's approved. The 4–8 week Metro Water lead time is the longest pole in the tent, and you can't receive a CO without the meter being in place.

Flip Timeline Guidance

ADU rough-in timeline in Nashville: Meter application (4–8 weeks, parallel), building permit (2–4 weeks), plumbing permit (1–2 weeks after building), rough-in execution (3–7 days). Start permit applications immediately on project start.

Pricing in Nashville

$2,500 – $8,000 for rough-in depending on scope, fixture count, and access

Nashville ADU rough-in (full kitchen + bath): $4,500–$9,000 depending on location, layout, and ejector pump requirements. Metro Water meter application fee separate. All quoted after site visit and plan review.

Flat-rate quotes. No hidden fees.

Get Nashville Quote

Call for Nashville

(734) 748-4831

24/7 Emergency Service Available

Rough-In Plumbing for Additions & New Layouts in Nashville — FAQ

What is the process for getting a Metro Nashville plumbing permit for an ADU addition?
The ADU plumbing permit process in Davidson County: (1) Confirm zoning allows ADU at your address — this is done via Metro Nashville Planning. (2) Submit the building permit application with site plan and floor plan showing the ADU layout. (3) The plumbing permit is typically pulled as a sub-permit under the building permit. (4) Apply for the Metro Water Services new water meter — this is the critical path item with 4–8 week lead time. (5) Once building permit is active and meter application is submitted, rough-in can begin. We handle steps 3–5 on behalf of our investor clients and flag the Metro Water lead time immediately so it doesn't surprise the project schedule.

Serving Nashville, TN

Rough-In Plumbing for Additions & New Layouts in Nashville — Get Your Quote

Fast, permitted, flat-rate rough-in plumbing for additions & new layouts in Nashville. No surprises, investor pricing available.

Licensed & Insured in Tennessee No Hidden Fees Investor & Volume Pricing 24/7 Emergency Response